The Last Two Weeks: A Day-by-Day Plan for Competition Entries.

By Adam Morgan24 November 20269 min read
The Last Two Weeks: A Day-by-Day Plan for Competition Entries

Concept locked, fourteen days left. A working schedule from freeze to upload, with the buffer days most teams forget to protect.

A competition entry is rarely lost in the last fortnight because of a bad idea. It is lost because the idea kept moving while the boards were being built, because the upload was left to the final hour, or because nobody agreed who owned the text. This plan gives the last fourteen days a shape: one freeze point, one visuals cutoff, one buffer day. Use it as a template and adjust the dates to your own brief.

The schedule assumes a small team, anywhere from one person to four, producing either a single large panel or a short multi-sheet set. It works the same way for a one-person entry. The only difference is that every role in the ownership list below lands on the same name.

Day 14: Lock the Concept and Write Down What Is Frozen

Article illustration

Start by defining "locked" in a form the whole team can read. Four things freeze today: massing, entrance, circulation logic and the one idea the jury must remember. Write them as four short lines on a single sheet. Everything else (materials, planting, furniture, facade rhythm) stays open to refinement. Those four do not move, and anyone proposing to move one has to say so out loud and get agreement.

Then reread the brief and the submission rules before doing anything else. Pull out board count, sheet size, orientation, word limits, anonymity requirements, file format and size cap. Build a one-page checklist from them and pin it where the team works. Competition rules are set by the organiser, so quote them from the organiser's own documents, not from memory or from last year's entry.

If the scheme is not yet modelled, drop it into Linea as a Massing block-out. In Linea the plan and the 3D model are one building, so a late change to a footprint cannot drift between the drawings and the views. That single property removes a whole class of last-week errors, where a plan says one thing and the hero render shows another.

Ask Corb in the Linea assistant chip questions about the drawing. Questions are free. Corb can read the model against your notes and will name planning or regulatory risks it spots, but it names them as risks, never as rulings. Whether the scheme complies stays with whoever carries the liability. Treat Corb as an aide-mémoire for the freeze list, not as a compliance check.

A frozen concept is a written one. If the four locked items are not on a sheet everyone has read, they are not locked.

Finish the day by assigning ownership. Name who owns drawings, visuals, text, layout and upload, and name one person as final signatory for each board. Without a named signatory, last-minute edits arrive from everywhere and nobody is accountable for the version that goes out.

Days 13 to 10: Build the Drawings and Lock Your Camera List

Article illustration

The next four days are for the technical drawings. Draft plans, sections and elevations from the model in Linea. Sections and elevations are cut from the model as real linework, so when a wall moves overnight the drawings follow. Saved views can be reissued after the model changes, which matters more than it sounds: the cheapest moment to catch a drawing that disagrees with the model is before it is on a board.

Decide the hero images now

Choose your hero images and their camera positions on day 13, not in week two. Place render cameras in Linea, save them as named views, and reissue them after any model change so every view stays in step with the scheme. A named camera list also forces a useful conversation: what does the jury need to see, and from where? A competition board for a library might need an entrance view, a reading-room interior and a section perspective. A pavilion might need one strong exterior and one night view. Settle the list and write it into the checklist.

Bring in site material and sketches

Import existing site material early. Linea takes DWG, DXF and IFC. Practice CAD files often hold twenty-odd drawings in one model space on shared layers, and the import dialog finds the separate drawings inside the file, so one click crops the import down to the site plan you need.

If the competition rewards sketch-led or hand-drawn diagrams, take them into Vector. Drop in a PDF, DWG or DXF as editable linework, or trace a photographed sketch into paths. The Paint Bucket colours the zones that sit between the lines, which is how a hand-drawn zoning diagram becomes a clean, legible board graphic without redrawing it. Keep line weights deliberate: a consistent pen-weight hierarchy across every diagram is one of the quickest ways to make a board feel designed.

Pick the sheet structure and stop

Compare two structures on paper before touching a template: a single large board against a multi-sheet set. Sketch both at thumbnail scale with the actual drawings and hero images placed in roughly the right positions. Pick one by day 10 and stop revisiting it. Reopening the sheet structure in week two is the most common way a team burns a day it does not have.

DaysLocked by end of blockOwner
13 to 12Plans, sections, elevations from the modelDrawings
12Named camera list, saved in LineaVisuals
11Site material imported, diagrams draftedDrawings
10Sheet structure chosen: one board or a setLayout

Days 9 to 6: Produce the Visuals Before the Layout Needs Them

Article illustration

Visuals come before layout because a board built around placeholder images gets rebuilt when the real ones arrive. Render the hero views from the saved Linea cameras, then refine in Image or the Retouch surface. Treat the exterior and the interior as separate jobs with their own lighting logic. An interior lit by overcast daylight and an exterior at golden hour can both be right individually and still fight each other on the same sheet.

Use Retouch for the fixes that eat evenings

Retouch handles the jobs that otherwise swallow the last week:

  • Enhance area re-renders a selected region at higher resolution with no prompt, which suits wide renders where a stretch of facade or paving has gone soft or repetitive.
  • Material swap replaces the texture of a selected area to match a reference you attach, as a toggleable layer. Use it on the facade the jury will read closely.
  • Re-light presets regenerate the whole document at a different time of day or weather as a new layer. If the golden-hour view fights the overcast one, align them here instead of re-rendering from scratch.

These actions use plan credits, and each shows its cost before it runs, so check the figure and decide whether the fix is worth it.

Keep the set coherent

One time of day, one weather condition and one entourage density across the board is stronger than four individually brilliant images that do not match. Jurors read a board as a single argument. Visual consistency tells them the scheme is resolved. Visual variety tells them the images were made in different weeks by different hands.

Variations that hold the scheme

On the canvas, you can ask Corb to spawn a small set of variations off one chosen render, varied along a single axis such as lighting or camera. A clause holding the geometry, massing and openings still is written into every prompt in the set, and the variations land idle, so nothing is charged until you run them. Be clear about what this is. It is a preservation instruction to the model, not a geometric lock, so always compare the results against the frozen list from day 14. The principle holds for any image generation you do at this stage: prompts may change atmosphere, light or material expression, and must never silently change the scheme.

Set a hard cutoff: no new hero images after day 6. Anything still unresolved becomes a retouch job, not a re-render.

Days 5 to 3: Assemble the Boards in Layout and Protect the Text

Open Layout in Sheet mode at A1 landscape, or choose the Competition template if the brief is a single panel. Turn on the layout grid, either Manuscript, Columns or Modular, so every element snaps to it. The grid is a reference overlay only and never appears in an export. If the brief asks for a multi-page set, Document mode gives you pages at A3 instead.

Place the drawings and renders first, then set the type. Layout carries a self-hosted type library of 300 families, with Inter as the default, and you can upload a practice font if the brief allows one. Keep the hierarchy strict: title, concept line, captions, small print. Four levels is enough. A fifth usually means a caption is doing a heading's job.

Write the concept statement last, and keep it short

Write the concept statement after the images are placed, because the images tell you which sentence the board actually needs. Select the text frame and ask Corb to fill that frame, then rewrite the result in your own voice. Check every figure against your project notes. Corb does not invent dimensions or areas, and it will ask for a number it does not have, but the check is still yours. Word limits in the competition rules are binding, so count the words against the checklist, not by eye.

Proof at true size

Export a vector PDF at true sheet dimensions and read it at 100 per cent on a second screen. Check line weights, small text and anything that rendered differently from the layout. A caption that looks fine zoomed to fit often reads too small at full size, and a hairline that looks sharp in the editor can vanish in print.

Run a fresh-eyes review

Find someone who has not seen the scheme and give them thirty seconds with the board. Ask them to state what the project is. If they cannot, the hierarchy is wrong, not the scheme. Fix the hierarchy: enlarge the concept line, remove a competing image, or give the hero render more room.

CheckHow
Sheet size and orientationCompare exported PDF dimensions against the day 14 checklist
Word countCount against the organiser's limit, per board
Line weightsRead the PDF at 100 per cent
AnonymitySearch every board, layer name and file property for names and logos
FiguresTick each number against the project notes

If a fresh reader cannot name the project in thirty seconds, fix the hierarchy before you fix anything else.

Days 2 to 0: Buffer, Final Export and Upload

Day 2 is a buffer day, not a work day. Use it only for corrections found in review, and decline new ideas, however good. It is the single most valuable day in the schedule, because it absorbs everything the plan could not predict: a file that will not export, a typo found by a fresh reader, a figure that did not match the notes.

Run the checklist line by line

Return to the checklist from day 14 and work through it line by line: file format, size cap, sheet dimensions, anonymity, filenames, word counts. Export the PDF, and export a PNG of each board as a fallback. A competition portal may accept one format and reject another, and a fallback you made on day 1 is worth more than a fix you make at 11pm.

Test on a different machine

Share a read-only Layout link, or send the PDF to a colleague on a different machine. If it opens and reads correctly there, it will open for the jury. Fonts, colour profiles and file sizes all behave differently from one machine to the next, and a second pair of eyes on another screen is the cheapest test there is.

Upload with room to spare

Upload at least four hours before the deadline. That figure is operational advice, not an industry statistic, and the reasoning is simple: an early upload leaves time for a rejected file, a failed checksum, a payment problem or an account issue. A failed upload at 4pm is a retry. A failed upload at 11:55pm is a disqualification. Check the organiser's own instructions for how the portal confirms receipt, and keep the confirmation.

Archive the same evening

Archive the live files before you sleep. A tidy project folder with the final model, the boards and the checklist is the starting point for your portfolio page, whatever the result. The images you rendered, the drawings you issued and the concept statement you wrote are all reusable, and they are much easier to find the night you submit than six months later.

Freeze the concept on day 14, stop making visuals on day 6, treat day 2 as untouchable, and upload at least four hours early. Everything else in the schedule exists to protect those four decisions.

The Plan on One Page

BlockGoalDone means
Day 14FreezeFour locked items written down, checklist pinned, owners named
Days 13 to 10DrawDrawings issued, camera list saved, sheet structure chosen
Days 9 to 6VisualiseCoherent hero set, no new renders after day 6
Days 5 to 3AssembleBoards laid out, text checked, fresh-eyes review passed
Days 2 to 0DeliverCorrections only, checklist cleared, upload confirmed early

The schedule works because each block ends with a decision that cannot be reopened. Write the freeze list tomorrow morning, put the cutoffs in the team calendar, and protect day 2 as if it were the deadline itself.